By Bruce Collins, Adam Zius
Introduction
Shotcrete can be an excellent material and application method for repair of reinforced concrete structures. Properly designed and applied shotcrete has low permeability and can provide excellent repair durability. The following are repair project examples using shotcrete.
Project #1-Pier 15 Repair Hoover Dam By-Pass Bridge
The new Hoover Dam bypass bridge is a composite concrete deck, arch, and steel superstructure bridge measuring approximately 1900 ft (579 m) long. The concrete arch span is approximately 1000 ft (305 m). Fire damage recently occurred on a single pier cap measuring approximately 10 ft (3 m) tall, 7 ft (2.1 m) thick, and 72 ft (2 m) long. The fire damaged the concrete cover along the bottom and corner along an approximate 25 ft (7.6 m) length pier cap. The joint venture partnership knew that hydrodemolition removal and proper concrete surface preparation along with shotcrete repair material would provide the desired durability. After an initial review of the project including access and the total quantity of repair material required, we recommended use of the dry-mix shotcrete process. The Federal Highway Administration (FHWA) on-site personnel, however, required extensive prerepair construction testing to prove the proposed repair materials and methods. Testing included:
- Mixture design submittals and material certifications;
- Shrinkage testing of the repair material;
- Compressive strength testing of the repair materials;
- Test panel production and shotcrete core grading; and
- High-pressure water blasting surface preparation and shotcrete-to-concrete bond strength testing using test panels.
Key shotcrete parameter design included a 28-day compressive strength of 6000 psi (41 MPa) and low-to-moderate shrinkage characteristics. A preblended dry-mix material was selected with a design compressive strength of 7250 psi (50 MPa). The mixture design consisted of Type I portland cement, silica-fume, and aggregate meeting ACI 506.2 gradation No. 2.
Shrinkage testing of the repair material was completed by an independent testing laboratory that mixed 7 lb (3.2 kg) of water with 66 lb (30 kg) of the dry preblended shotcrete. The resulting slump of the material was 1.5 in. (38 mm). Three 3 x 3 x 11-1/4 in. (76 x 76 x 286 mm) prisms were cast and cured per ASTM C157. Drying shrinkage measurements were completed at 7, 14, 21, and 28 days. Average results were 0.047%, 0.064%, 0.075%, and 0.076%, respectively, at 28 days. The International Concrete Repair Institute (ICRI) categorizes shrinkage in its Technical Guideline No. 03733, “Guide for Selecting and Specifying Materials for Repair of Concrete Surfaces.” In the guideline, 0.025 to 0.050% is considered low shrinkage and 0.050 to 0.10% is considered moderate shrinkage for 28-day test results.
Three separate test panels were constructed. One 4 ft x 4 ft x 5-3/4 in. (1.2 m x 1.2 m x 146 mm) unreinforced lumber construction panel was prepared and shot at the repair contractor’s facility. Initial curing was completed using water foggers. Three cores were extracted for compressive strength testing and visual core grading per ACI 506.2. Visual grading showed excellent results with all cores achieving an ACI Grade 2 or better. Compressive strength testing results averaged 8180 psi (56.4 MPa). The second test panel was constructed using No. 11 (35 m) reinforcing bars at 10 in. (250 mm) on center with No. 4 (13 m) bars at 6 in. (152 mm) on center over the larger bars. The test panel size was 4 ft x 4 ft x 5-3/4 in. (1.2 m x 1.2 m x 146 mm). This panel was shot at the repair contractor’s facility and three cores were extracted including the reinforcing and visually graded by FHWA officials. All results were ACI Grade 2 or better. The third test panel was built at the joint venture contractors’ facility and was constructed using the concrete mixture design used for the original pier cap construction. The concrete panel was constructed with exposed No. 11 (35 m) bars and No. 4 (13 m) stirrup bars similar to the pier cap reinforcing steel placement. The concrete test panel was shipped to the repair contractors’ facility. Surface preparation of the 6 x 6 ft (1.8 x 1.8 m) concrete test panel was completed using a 20,000 psi (138 MPa) pump delivering water at approximately 12 gal. (45 L) per minute. The test panel was shot using the designated repair shotcrete. Initial curing was completed using fog sprayers. After 7 days of curing, shotcrete-toconcrete bond tests were completed per the ICRI guideline. An average direct tensile shotcrete-toconcrete bond strength of 259 psi (1.78 MPa) after 14 days was obtained. After completion of all the testing, the repair contractor mobilized to the project site. Surface preparation was completed by a hydrodemolition contractor per the high-pressure water specifications, similar to that used in the testing procedure. The shotcrete repair contractor installed approximately 60 ft3 (1.7 m3) of shotcrete using a dry-mix shotcrete gun driven by a 375 cfm (10.6 m3/mm) compressor.
Project No. 2—Reinforcing Steel Corrosion Repair in Industrial Environment
A coal-fired electrical generation station located in the desert southwestern U.S. was experiencing reinforcing steel corrosion in certain components of the concrete draft cooling towers on the property. The conventionally reinforced concrete lower rings of the fan stack assemblies were deteriorating from reinforcing bar corrosion. An investigation revealed that the wetting and drying action combined with low (3/4 in. [20 mm]) concrete cover was allowing the corrosion process to initiate. Results of the investigation revealed that approximately 15% of the 24,730 ft2 (2297 m2) of concrete area was delaminated or spalled and required repair. First, it was important to develop a repair scheme that addressed the source of corrosion.
The repair scheme consisted of installing a thick epoxy coating on the inside face of the concrete assembly to cut off the vapor drive through the concrete. This work was completed during two separate 30-day plant shutdowns for maintenance periods. Once the vapor drive was shut down and the concrete humidity level was reduced, the shotcrete repairs were started. The repair material selected was a prepackaged 5000 psi (34 MPa) 28-day compressive strength product with aggregate gradation No. 1 per ACI 506. Dry-mix installation was selected due to the large number of repair locations coupled with the small average area per location. The repair locations were on a vertical surface, and the use of dry-mix shotcrete eliminated the need for the use of concrete formwork required for casting repairs. The repair material was tested for permeability. The permeability requirement allowed for compatibility with passive cathodic protection anodes installed along the perimeter of each repair location. Delaminated concrete was removed using 15 lb (7 kg) chipping hammers. Surface preparation was completed using dry sandblasting. The shotcrete was installed over a 2-week period during operation of the cooling towers. Shrinkage cracking occurred in greater amounts than normally experienced due to the elevated temperatures of the concrete substrate and the difficult curing conditions. A silane sealer was applied to the shotcrete upon full curing. Corrosion current, half cell potential, and resistance measurements were taken using a linear polarization tool prior to and after repair completion. Concrete resistance, an indirect measure of concrete humidity levels, improved nearly nine fold from 10 kilo-ohms to 90 kilo-ohms resistance. Reinforcing bar corrosion currents improved from 150 mm per year dissolution to 25 mm per year. Finally, corrosion potential improved dramatically. At the conclusion of the project, it was determined that the reinforcing steel is once again in a passivated state.
Project No. 3—Pre-Cast Concrete Cylinder Pipe Strengthening
An electrical generation station in western Colorado was experiencing corrosion in the prestressing wires through sections of their precast concrete cylinder pipes. The water transfer pipes supply water between the power station and the cooling towers. During a 2-week shutdown period, testing was conducted to determine the extent of the corrosion in the wires. Testing found that one spool, an 18 ft (5.5 m) section of pipe, was compromised to the point that external post-tensioning was required. The spool ran 18 ft (5.5 m) in length, with a 9 ft (2.7 m) diameter, and was located approximately 20 ft (6.1 m) below grade. A large excavation was required to gain access to the damaged spool. The excavation was made approximately 25 ft (7.6 m) deep with a 60 ft (18 m) diameter, with sloped sidewalls for safety.
The water transfer pipe containing the damaged spool ran parallel and next to another water transfer pipe. Once the damaged spool was exposed, a trench box was placed between the two water transfer pipes for safety. Prior to complete excavation, each end of the spool was excavated and tendons were installed to help support the dead load. The spool was then fully excavated and the outer concrete shell was sound tested with the engineer of record. The investigation found that the exterior concrete shell had debonded from the interior and a large crack spanned half the circumference of the spool. It was determined that the outer shell should be removed and further examination of the crack was necessary.
The exterior shell was excavated using pneumatic hammers. Upon inspection, it was found that a significant number of prestressing wires were corroded and broken. The large crack that ran around the exterior shell continued into the interior concrete shell. Core samples were taken to determine the depth of the crack within the internal concrete shell. If the crack extended the full depth to the steel fiber liner allowing corrosion, spool replacement would be required. The core sample showed that the crack did indeed extend full depth, however, the liner showed no signs of corrosion. With a corrosion-free liner and solid inner core, a post-tension repair was viable.
The 18 ft (5.5 m) spool was then wrapped with a total of 53-1/2 in. (12.7 mm) diameter sevenwire strands at 4 in. (100 mm) on center. The strands on each end of the spool were stressed to a force of 47 kips (209 kN), followed by a sequence of stressing every other tendon. Conductivity between the tendons and the steel liner was established and verified. Aggregate was used to fill the bottom of the excavation prior to applying the shotcrete, preventing any ground water from interfering with the mixture. A low shrinkage, fiber-reinforced wet-mix shotcrete was specifically designed for this project with the local concrete company. The shotcrete mixture was pumped through a 2 in. (50 mm) nozzle and a shotcrete cradle was created at the base of the spool. This shotcrete cradle acted as the footing, providing the necessary support to prevent slumping. The new exterior shell was shot, providing 2 in. (100 mm) of cover over the external post-tension stands. The shotcrete shell was then covered with wet burlap sacks and plastic for proper curing. Once the shotcrete shell had cured for 3 days, the excavation was filled and compacted back to the original grade.
Shotcrete is a versatile repair technique. Its physical properties provide numerous repair solutions in many different environments and situations. These three case histories provide examples of the versatility of the shotcrete process.
This can do the technique!
proven approach for boosting happiness, efficiency and also productivity .
[url=https://d3n8a8pro7vhmx.cloudfront.net/centralemarseille/pages/4/attachments/original/1674257285/okinawa-flat-belly-tonic-49bc6s4i8.xml?1674257285]Okinawa Flat Belly Tonic reviews
[/url]
Achieving goals, success and efficiency is a wind with Phenomenal!
Enjoy daily galleries
http://vivica.pornhorace.energysexy.com/?ellen
porn blue ray 1080 p horny girl porn videos brunette porn actresses rankings orihimie anime porn 3d monsters porns
You’re outstanding, currently your life can be also!
Hello
It is a reality of life that you will suddenly die some day and maybe that will happen soon. Therefore, you must find out WHO IS OUR SAVIOR? Before you die and face him.
Scrifice equal love ?
Go to
https://internetmosque.net/saviour/index.html
and find out the TRUTH before it is too late
Piece
[b]медицинский центр в Москве[/b]
[url=http://online.medspravki-ru.com/2020/02/07/spravka-o-vakcinacii-ot-grippa/][img]https://i.ibb.co/z2W1KRh/136.jpg[/img][/url]
Медицинское учреждение – это организация, занимающаяся диагностикой и лечением болезней. В зависимости от типа медицинского учреждения оно может быть государственным или частным, больницей, клиникой, диспансером, поликлиникой или амбулаторией. В медицинском учреждении работают врачи различных специальностей, а также медицинские сестры, лаборанты, диспетчеры и другие сотрудники. В медицинском учреждении проводятся диагностические и лечебные процедуры, исследования, приемы врачей, проводятся дополнительные консультации. В зависимости от типа медицинского учреждения в нем могут быть проведены операции, предоставляться медицинские услуги и т.д. В медицинском учреждении принимаются платные и бесплатные пациенты, а также могут быть предоставлены государственные социальные программы. Основная цель медицинского учреждения – предоставление качественной медицинской помощи пациентам [url=http://online.medspravki-ru.com/product/spravka-iz-narkologicheskogo-dispansera-2/]психоневрологический диспансер справка в гибдд[/url] нарколога и психиатра справку купить в москве
Читать всю статью: http://www.massmed.org/
Expedita iusto quis id quis laborum nulla ea. Atque consequuntur tempora et deserunt dolor commodi dolorem. Voluptatem maxime ut sit. Accusantium aut ut enim eveniet numquam praesentium nostrum. Hic cumque explicabo ipsam corporis et rem. Laborum iure et minima repellat.
Odio quae rerum dolorum sit. Molestiae cum ut est est ipsum porro. Aut quasi rem laborum fuga eius nihil sed consequatur. Vero aut accusamus incidunt quibusdam. Aspernatur assumenda deserunt placeat omnis quo.
[url=https://in-krmp.org]krmp.cc[/url]
Cum qui qui nihil fugit harum. Illo iusto tempora repellendus aut. Minima repellat aut quidem rerum fugiat aut. Cum voluptas maiores officiis. Incidunt ut sed corporis autem soluta repellendus quasi. Sint amet facilis cupiditate in cum fugit ut voluptas.
Quasi doloremque autem explicabo. Est natus accusamus sequi expedita dolor. Reprehenderit et eligendi dolore nulla architecto.
Quibusdam modi possimus deserunt eum. Occaecati iusto voluptatem nihil molestiae. Sint pariatur assumenda quo adipisci. Voluptates ut sed aut quisquam et occaecati. Provident consequatur amet molestiae. Odio temporibus ea consequuntur minima sed.
Et explicabo ex hic beatae et delectus id ut. Illo minus expedita aut adipisci est. Accusamus provident maxime beatae quam sint dolor. Voluptas fuga possimus libero. Itaque iure qui est perspiciatis.
Atque est fugit reiciendis. Amet voluptatum quas aut sed placeat illo tempora et. Voluptatem et totam dolorem tempore in. Tempora fuga dolores dolores.
Sed temporibus sint voluptatem debitis neque soluta mollitia. Illo quia ducimus non. Similique dolorum impedit voluptatem odit. Debitis et placeat aut illo.
Id error mollitia enim eos ullam delectus tenetur debitis. Qui sit magnam ab nihil distinctio enim in. Necessitatibus vitae eaque natus distinctio.
Eum quisquam est recusandae quia animi. Aut et ea consequatur labore eius velit et. Mollitia exercitationem quaerat maxime.
кракен магазин
https://kramp-cc.com
Non quo modi et. Libero expedita sed qui illum beatae est ipsum. Repellendus veniam qui fuga nulla ut quam ut. Commodi excepturi et nisi eligendi hic culpa. Veniam cumque voluptatibus perspiciatis.
[url=https://k2web.su]in.k2web.cc[/url]
Esse ratione dolore deleniti vitae enim quisquam qui. Mollitia quia et soluta ut quisquam. Qui nihil est quo quas autem voluptatibus amet quibusdam. Dolor eaque voluptates dolores minima quo officia consectetur. Est quos ad sit quas esse nobis et. Omnis nihil occaecati ea ut modi voluptatum accusamus aperiam.
Voluptatibus perferendis est et consequatur. Impedit eum consectetur ea temporibus labore quo molestias. Esse laudantium unde dolores modi eaque nihil.
Facere veritatis aut qui voluptas. Dicta quam impedit et iure. Nisi rem repellendus expedita qui praesentium ipsa harum unde. Harum quam provident quisquam. Ut eos consequatur doloribus voluptatem molestias officia sunt.
Dolore minus est saepe culpa et. Modi voluptas quas corrupti maxime non. In ipsa sint distinctio a voluptas et qui rerum. Accusamus et fugiat molestias magni odit totam. Est quia aspernatur et et maiores.
Voluptatibus animi amet sed et iste quisquam. Magnam praesentium sint dolor velit earum. Optio architecto vel dolorem omnis expedita. Veritatis vero dolor quo sapiente itaque quo deleniti ea. Soluta dolorum ut soluta odit quaerat.
in.k2web.cc
https://in-k2web.com
[url=https://k2web.net]in.k2web.cc[/url]
Hot galleries, thousands new daily.
http://spydialogue.adablog69.com/?piper
free video sarah palin porn alyssa hall free porn lexi marie full porn videos little man porn free mobile porn wallpapers
Hardcore Galleries with hot Hardcore photos
http://lesbianstuff.beautifulromanticdp.hotnatalia.com/?paige
kristy goulding porn video porn star kaycee jordan why men watch porn bravo dirty porn sluts catholic porn sites
New hot project galleries, daily updates
http://tera.oatrick-ultrafilms.tubered69.com/?karen
raquel porn free moblie porn vidoes round brown porn lake tapps porn classic porn torrents
New sexy website is available on the web
http://forcedcummyporn.bloglag.com/?post-alexandrea
cum toothpaste porn fee naked porn pics porn directory tubes free picture porn blsck porn for guys
Free Porn Pictures and Best HD Sex Photos
http://bestlimericksever.fetlifeblog.com/?maggie
free porn mo nica sweetheart shannon black porn best porn movies on netflix porn daughter spanking video machinefucking porn
selector 21gg
https://selektorkazinogame.ru
В будущем можно будет играть в онлайн-казино со своего смартфона. В игру играют на экране компьютера и использует специальное программное обеспечение, которое генерирует случайные числа для игры. Игрок выбирает сумму денег, а затем делает ставки на результат случайного числа, сгенерированного программой.
Numquam distinctio quos deserunt corrupti exercitationem impedit. Et mollitia sed qui quia cumque. Quas sint et quo quo quia quibusdam culpa.
Dolore quidem quasi et tempore dolorum aut. Accusamus nihil facere sunt laboriosam quos doloremque eligendi enim. Quaerat maiores a unde.
[url=https://omgomgomg5j4yr4mjdv3h5c5xfvxtqs2in7smi65mjps7wvkmqmtqd.net]omgomg onion[/url]
Exercitationem dolor nulla natus maxime dicta blanditiis. Eos distinctio aspernatur optio. Ex accusantium consequuntur quibusdam vel fugiat. Est ad molestiae dignissimos. Officiis possimus et minima ipsum exercitationem. Nesciunt suscipit exercitationem sunt eum numquam.
Eligendi et enim aut ad magnam. Optio quo autem architecto molestiae eum. Aut pariatur quae totam voluptas. Nesciunt quia et consequuntur.
Mollitia modi soluta ut et. Possimus qui reiciendis sint doloremque. Dolor dolore consequatur exercitationem inventore earum. Quia ea nisi nihil rerum aut aut at.
Voluptatem soluta libero sint laboriosam accusantium id ea illum. Nemo temporibus autem omnis magni qui odit et. Id quam perferendis nostrum. Et voluptates ut ut.
omgomg onion
https://omgomgomg5j4yrr4mjdv3h5c5xfvxtqqs2in7smi65mjps7wvkmqmtqd-onion.cc
Eine qualitativ hochwertige Website uber das, was Sie in Frankfurt brauchen, ist Schlussel abgebrochen im Schloss – Wie bekommt man ihn raus?.